• Lakewood Stadium

    Atlanta, GA
  • Lakewood Stadium

    Atlanta, GA
  • Lakewood Stadium

    Atlanta, GA
  • Lakewood Stadium

    Atlanta, GA
  • Lakewood Stadium

    Atlanta, GA

A New Sustainable Stadium

The Lakewood Stadium began as a renovation project, but after our site analysis revealed concrete and steel deterioration as well as Life Safety Issues, APS decided to build a new stadium instead.

This new stadium is designed to withstand years of weather exposure, as well as adhere to high standards of environmental responsibility by meeting LEED Silver requirements. The space below the seating areas is designed to house locker room facilities, storage rooms and offices for the APS Athletic Department.

Project Specifics:


LAKEWOOD STADIUM
70 CLAIRE DRIVE, ATLANTA, GEORGIA 30301
NEW REPLACEMENT STADIUM AREA:
40,200 SF of conditioned space
DESIGN CONTRACT AWARD: $13,585,030
FINAL COST: $13,585,030
CONSTRUCTION DELIVERY METHOD:
Construction Manager

CONSTRUCTION PLANNED: 12 months
FINAL DURATION: 12 months
SUBSTANTIAL COMPLETION: November 17, 2011
ATLANTA PUBLIC SCHOOLS: Mr. Jere J. Smith III, AIA, Director Of Capital Improvements
CONTRACTOR: Winter Construction